The Office for Rail and Road has proposed lower charges for passenger trains which use the High Speed 1 line from London St Pancras to the Channel Tunnel, and halving charges to freight, in its Draft Determination of HS1 Ltd’s spending plans.

The Draft Determination sets out ORR’s view of HS1 Ltd’s five-year spending plans for the high speed line, from 2025 to 2030. ORR was able to identify specific areas in the company’s spending plans where further improvements can be made, resulting in savings to passenger and freight train operators.

In its detailed review, ORR says that HS1 Ltd has produced a good 5-year plan that showed improvement from the plan for the previous five year control period, and highlights successes that HS1 Ltd has achieved in the current control period, 2020-2025.

The successes include improvements to the way the company maintains and renews its track assets using more detailed asset data, which ORR called for in its last review of the company’s plans, in 2020. ORR is calling for HS1 Ltd to take a similar approach to other assets – such as its signalling, and the lifts and escalators at its stations, so that those assets are maintained as efficiently as possible now, and into the future.

ORR has also reviewed the costs for stations on the line for the first time (previous reviews were conducted by the Department for Transport), including St Pancras, and has identified opportunities for improving the way the stations are managed, to reduce their costs.

Feras Alshaker, Director, Planning and Performance at the ORR, said:

“The High Speed 1 line is a vital connection between the UK and Continental Europe, and makes a crucial contribution to the UK economy, supporting growth.”

 It is important that it continues to be a resilient, high performing network for both passengers and freight users.”

"The detailed scrutiny and challenge we’ve applied to HS1 Ltd’s plans should see the costs of operating on the line reduce significantly, giving savings for both international and domestic operators over the next five years, with benefits for passengers and freight users."

Image Credit: Istock

Rail technology Magazine i144

RTM Issue 144

THE FUTURE OF RAIL IN THE NORTH

Focusing on the latest developments, innovations, and policy impacts in the UK rail industry, with a particular emphasis on sustainability, infrastructure upgrades, and future technological advancements.

More articles...

View all
TransCityRail Banner

TransCityRail

Mids \ 27.02.25
South \ 10.07.25
North \ 06.11.25

TransCityRail is a series of regional, interactive and insightful events across the country bringing together leaders, collaborators, problem solvers and innovators in a creative and invigorating way.
 

This series of events supports and informs the whole of the rail industry and connects suppliers with buyers, specifiers, leaders and decision-makers looking to procure a wide variety of innovative products and services for their region.

Rail Technology Magazine Podcast

Listen to industry leaders on everything within rail

Whether it's the latest advancements in rail technology, policies, innovations, or the challenges facing the rail industry providers, we cover it all.

 

Join us as we engage with top rail professionals, industry leaders, and policy experts to bring you insightful conversations that matter.